In Plan View, you design your plan, which includes the building and sequencing of tasks and the triggers that execute your sequence of tasks. |
Plan View Page |
The main panel is the plan canvas, where you build your plans.
On the right side is the context panel. Depending on what you select in the plan canvas, a different set of context options is displayed.
Tip: To rename the plan, click the plan name in the top bar. |
Zoom Options:
You can zoom the plan canvas to display areas of interest in the plan graph.
The zoom control options are available at the right side of the canvas. The following are the available zoom options:
Tip: You can use the keyboard shortcuts listed in the zoom options menu to make quick adjustments to the zoom level. |
NOTE: By default, the plan view page always opens in Zoom to fit option and it does not remember the previous zoom and position. |
Other options:
Run: Run the plan. You can track progress of your plan run.
Tip: You can apply overrides to flow parameters through the Parameters tab. See Plan View for Flow Tasks. |
See Plan Runs Page.
Rename: Modify the name and description for your plan.
For more information, see Create a Plan.
To create a trigger, you specify the time and frequency that the plan is to be executed.
NOTE: Plan owners can create triggers for their plans. Other users must have the appropriate privileges to create triggers for the plan. |
Create plan trigger |
UTC
in the drop-down.Time zone settings set in the drop-down are used with the cron schedule.
Saved trigger |
To disable the trigger, click the slider.
NOTE: If you disable a trigger, no new scheduled executions of the tasks in the plan occur. You can still manually trigger plan runs. |
When you create or select a task, you can modify its settings through the context panel on the right.
Tip: To rename the task, click the task name in the context panel. |
Task context menu options:
You can review the details of individual executions of your plan. Click the Runs link in the upper-right corner.
Run details |
The latest plan run is displayed. You can review the progress of individual tasks throughout the plan run.
NOTE: When a plan run begins, a snapshot is taken of the plan. Subsequent changes to the underlying flows could impact the outcome of the flow tasks when they are later executed during the plan run. |
You can track all of the runs across all of your plans. See Plan Runs Page.
You can gate the execution of a task based on the completion status of its previous task. Click the line connecting the two tasks and select one of the following options:
For more information, see Create a Plan.
You can can execute one or more tasks in parallel by clicking the plus node icon and selecting one of the following options:
NOTE: Nodes added in a sequence are separated by a plus node. A node added in parallel has two plus nodes separating it from the parent node; one for adding nodes in parallel and other for adding a node in sequence. |
The following icons indicate the results of the execution of a task:
Icon | Task Status |
---|---|
Task successful | |
Task failed | |
Task skipped. Task was not executed due to unmet conditions. | |
Task canceled by user | |
![]() | Task in progress |
Task pending |
For more information, see Create a Plan.
To cancel a plan that is currently running, please do the following: